Builder charging more than the quote: what the law says
When the price goes up because the work changed, it's a variation, and your state's law sets the steps before you pay.
If the builder wants more than the quoted price because the work has changed, the change is a variation, and it should be in writing, priced and signed before you pay anything extra. In Queensland the builder can't start the varied work until you agree in writing (Schedule 1B, section 40(5)) and can't require an increase before the varied work starts (section 41(3)). In Victoria, a builder who didn't follow the Act's steps can't recover money for a variation unless VCAT allows it (sections 37(3) and 38(6)).
Not legal advice — your contract's own variation clause matters too.
When an increase can be paid, by state
What each state's law says about paying for an agreed variation, and where it leaves the timing to your contract.
| State | When an agreed increase can be paid |
|---|---|
| New South Wales | Your contract's payment clause: the Act's variation term doesn't deal with it |
| Victoria | Your contract's payment clause |
| Queensland | Not before the varied work starts, and when the document says (Schedule 1B, sections 41(2) and 41(3)) |
| Western Australia | Your contract's payment clause |
| South Australia | Your contract's payment terms |
| Tasmania | As the variation document says: how progress payments are affected (section 18(2)) |
| Australian Capital Territory | The contract's clause governs |
| Northern Territory | The contract's clause governs |
Where the law limits what the builder can charge
Victoria
A builder can't recover any money for a variation they asked for unless they complied with section 37 and can show it was made necessary by circumstances they couldn't reasonably have foreseen when the contract was signed, and can't recover any money for a variation the owner asked for unless they complied with section 38 — in either case unless VCAT is satisfied there are exceptional circumstances or the builder would suffer significant or exceptional hardship, and that it would not be unfair to the owner. Where the money can be recovered, it is the cost of the variation plus a reasonable profit (sections 37(3), 37(4), 38(6) and 38(7)).
Queensland
Starting the varied work before the owner agrees in writing is an offence: 20 penalty units (Schedule 1B, section 40(5)).
A change, or an allowance?
Not every increase is a variation. If the extra is for a prime cost item or a provisional sum — an allowance in the contract for something not yet chosen or priced — the price moves with the actual cost under the contract's clause on allowances.
In Victoria the builder must give you a copy of any invoice or receipt behind a prime cost item or provisional sum as soon as practicable after receiving it (section 23), and it is an offence to put an allowance in the contract below the reasonable cost (section 21). Western Australia has the same offence for an allowance understated below the least it could reasonably cost (section 12).
What to do
- Ask the builder for the variation in writing: what changes, the price line by line with GST, and the new contract price.
- Check whether the extra is a change to the work or an allowance in the contract.
- If you don't agree with it, don't sign it, and tell the builder in writing why.
- If the change was only agreed on site, write it down yourself and send it to the builder to sign: ask your builder to put it in writing.
Can the builder charge before doing the work?
New South Wales
The variation clause doesn't deal with when a variation is paid — your contract's payment clause does. What the Act does require is that the variation is in writing and signed by or on behalf of both of you (Schedule 2, Part 1, clause 1(2)), so get the signed, priced variation before you pay anything extra.
Victoria
The order the Act sets is: written notice, your signed consent, then the builder can give effect to it (section 37(2)). And a builder who asks for a variation can't recover any money for it unless they followed section 37 and can show the variation was made necessary by circumstances they couldn't reasonably have foreseen when the contract was signed — or VCAT allows it in exceptional circumstances (section 37(3)). For when an agreed variation is paid, look at your contract's payment clause.
Queensland
No. Section 41(3): an increase in the contract price from a variation can't be required to be paid before the varied work starts. The variation document itself has to say when the increase is paid (section 41(2)).
Western Australia
For when a variation is paid, look at your contract's payment clause. What section 7 requires is that the variation is written, costed, dated and signed by both of you, with your copy before the work starts — so get that before you pay anything extra.
South Australia
The Act treats the variation as a contract of its own (section 3) that has to be in writing and signed by both parties (section 28). For when it's paid, look at your contract's payment terms — and don't pay for extra work that isn't in a signed variation.
Tasmania
The variation document itself has to say how progress payments are affected (section 18(2)) — so the payment timing should be on the page you sign. Where it adds work, the document has to be in place before that work starts.
Australian Capital Territory
The Building Act 2004 has no statutory rule for variations, so your building contract's variation clause governs. Get it in writing, priced, and signed by both of you before the work — which is what every state that does legislate asks for.
Northern Territory
The Building Act 1993 has no statutory variation rule either; the contract's variation clause governs. Same advice: in writing, priced, signed by both, before the work.
Sources
- Home Building Act 1989 (NSW): Schedule 2, Part 1, clause 1(2). Read 07/10/2026.
- Domestic Building Contracts Act 1995 (Vic): sections 21, 23, 37, 37(2), 37(3), 37(4), 38(6), 38(7). Read 07/10/2026 and 08/10/2026.
- Queensland Building and Construction Commission Act 1991 (Qld): Schedule 1B, sections 40(5), 41(2), 41(3). Read 27/09/2026 and 07/10/2026.
- Home Building Contracts Act 1991 (WA): sections 7, 12. Read 27/09/2026 and 07/10/2026.
- Building Work Contractors Act 1995 (SA): sections 3, 28. Read 27/09/2026.
- Residential Building Work Contracts and Dispute Resolution Act 2016 (Tas): section 18(2). Read 27/09/2026.
- Building Act 2004 (ACT). Read 27/09/2026.
- Building Act 1993 (NT). Read 27/09/2026.
Ask your builder to put it in writing
- $9.90 to send it. Your builder signs free, and the preview PDF is free.
- Your builder signs from a link. We email it to them; they sign on a phone or a computer, no app or account. If they won't sign, you're told why.
- Follows your state's rules. It asks for what your state requires and prints its statement, and the PDF ends with a signing record: who signed, when, and from which device.
See a signed example (PDF)A fictional job, signed by both parties.