Security of payment in Queensland
What the Building Industry Fairness (Security of Payment) Act 2017 (Qld) sets for payment claims, payment schedules and adjudication.
Payment claims, schedules and adjudication
| The rule | In Queensland | The source's words |
|---|---|---|
| Who can make a payment claim | A person who is, or claims to be, entitled to a progress payment (section 75(1)) | “who is, or who claims to be, entitled to a progress payment may give a payment claim” Building Industry Fairness (Security of Payment) Act 2017 (Qld) |
| A contract with a resident owner | Left out, to the extent the contract is for a building where the owner lives or intends to live (section 61(2)(b)) | “where the resident owner resides or intends to reside” Building Industry Fairness (Security of Payment) Act 2017 (Qld) |
| The payment schedule | Within 15 business days after the payment claim is given (section 76(1)(b)) | “15 business days after the payment claim is given to the respondent.” Building Industry Fairness (Security of Payment) Act 2017 (Qld) |
| Applying for adjudication | Within 30 business days after the claimant receives the payment schedule; the Act sets its own periods for the other cases (section 79(2)(b)) | “30 business days after the claimant receives the payment schedule” Building Industry Fairness (Security of Payment) Act 2017 (Qld) |
| When a progress payment is due | On the date the contract sets, or else 10 business days after the payment claim is made (section 73(1)(b)) | “on the day that is 10 business days after the day a payment claim for the progress payment is made” Building Industry Fairness (Security of Payment) Act 2017 (Qld) |
Not legal advice — your contract's own terms matter too.
Variations in Queensland
- The builder must not start the varied work before the owner agrees to the variation in writing (Schedule 1B, section 40(5); 20 penalty units).
- The owner must get a copy in writing before the earlier of 5 business days after the agreement and the start of the varied work (section 40(2)); it may be given by email (section 40(3)).
The rest of Queensland's variation rules, and the form set to them: variations in Queensland.
Sources
- Building Industry Fairness (Security of Payment) Act 2017 (Qld): sections 61(2)(b), 73(1)(b), 75(1), 76(1)(b), 79(2)(b). Read 24/10/2026.
- Queensland Building and Construction Commission Act 1991 (Qld): Schedule 1B, sections 40(2), 40(3), 40(5). Read 27/09/2026.
Fill in the variation
- $9.90 to send it, or twenty for $29 ($1.45 each). The builder signs free.
- The builder signs from a link. We email it to them; they sign on a phone or a computer, no app or account. If they won't sign, you're told why.
- Follows your state's rules. It asks for what your state requires and prints its statement, and the PDF ends with a signing record: who signed, when, and from which device.
See a signed example (PDF)A fictional job, signed by both parties.